June 2020

PWSA Delays Stormwater Project, Declines Request to Model Improvements Without Shuttle Roadway

On June 18, the Pittsburgh Water and Sewer Authority (PWSA) held a Zoom meeting to discuss the Four Mile Run Stormwater Improvement project and its revised schedule. A May 18 email from the PWSA stated in part, “Additional modeling and design effort have caused a delay to the overall project construction schedule. We originally anticipated starting construction this fall, but it is now anticipated to begin in 2021.”

Chief of Program Management Alex Scuilli began the meeting by acknowledging that “people are waiting for stormwater relief.” He assured attendees, “We think we have the solution [and can provide] a level of storm protection that will be very good for residents.”

However, further discussion of the updated model revealed an apparent scaling back of protection: According to slide 17 of PWSA’s June 2020 presentation, “Designing for a 10-year event was determined to be a cost-effective solution for reduced flood risk.” Notes from a February 22, 2019, meeting at the mayor’s office (obtained via Right-to-Know request) recorded Pittsburgh mayor Bill Peduto’s chief of staff Dan Gilman “wonder[ing] if instead of a 25-year storm, which is what current development designs for, should we be designing for a larger storm event.”

PWSA’s presentation calls out two previous floods in The Run: one 25-year event in 2011 and one 75-year event in 2009. It does not mention other events, such as a 2019 flood that included higher elevations in the neighborhood and a 2016 flood that trapped a resident and his son on the roof of their car.

Run residents have asked the PWSA Board to create a model for the Four Mile Run Stormwater Improvement project that excludes the controversial Mon-Oakland Connector (MOC) road through Schenley Park. MOC opponents contend that the MOC—a development project designed to lure corporations to Hazelwood Green—should not take precedence over the stormwater project. The core project in Schenley Park has long been considered “technically challenging” even without incorporating a new road.

Department of Mobility and Infrastructure (DOMI) director Karina Ricks commented, “We firmly support [PWSA’s] decision to take the time needed to ensure the massive stormwater investment we are making is the right one to best address the stormwater impacts that have affected The Run for so many years. The Mon-Oakland project will proceed concurrent with the PWSA green infrastructure project, thus our timeline is adjusted accordingly as well.”

Asked whether the PWSA has created a model without MOC or intends to do so, PWSA acting senior manager of public affairs Rebecca Zito responded, “The mobility project is a planned project and our model has taken into consideration that it would be constructed. Not including it would set false expectations and provide an unrealistic assessment for advancing the stormwater project. We appreciate that residents from the Run took the time to address the Board in March about this project. The Board heard your request to commission a model for the stormwater project without the mobility corridor project, unfortunately, we were not directed to do so.”

Five of PWSA’s six current board members were nominated by Mayor Peduto, a longtime proponent of MOC who faces an estimated $150+ million budget shortfall this year because of COVID-19. In contrast to PWSA’s stormwater project, which addresses a clear public safety issue and will be financed by the PWSA itself, the City-funded MOC project demonstrably fails to benefit residents in the neighborhoods it affects. By all appearances, Mr. Peduto’s priorities are the only reason the PWSA would view cancelation of the MOC as “an unrealistic assessment.” 

Contact the PWSA

412-255-2423
www.pgh2o.com/report-an-issue