These matters are not easily addressed. Yet when attendees asked about them, DOMI project manager Michael Panzitta responded, “That’s a good point” or, “We’re looking into that.” How has DOMI not heard the same resident concerns since 2018, when the Sylvan Avenue Trail was first proposed as phase 2 of the Mon-Oakland Connector shuttle road between Oakland university campuses and the Hazelwood Green development?
Community input
Discussion of this trail began with the Mon-Oakland Connector (MOC) instead of the communities in its path. Public meetings about development and infrastructure projects should focus on dialogue, not checking the “community engagement” box in a rush toward predetermined outcomes. Since 2022, Junction Coalition has been calling on the city to adopt our guidelines for public engagement, including announcing meetings at least 14 days in advance and posting the meeting slides with the announcement.
The design presented bore a striking resemblance to the MOC. Controversy plagued the plan partly because of dishonest tactics used to force it on affected communities. Opacity was and is its hallmark: inadequate community outreach for public meetings, evasive answers and an unwillingness to clearly define the scope of and intentions behind each phase of the project.
For example, while holding public meetings about the shuttle road in 2018, DOMI hid its grant applications for work on the Sylvan Avenue portion of the road.
Before informing affected communities about the MOC through a Pittsburgh Post-Gazette article, former mayor Bill Peduto’s administration filed a fraudulent grant application for the project for $3 million and then tried to cover it up, violated the Pennsylvania Sunshine Act, and repeatedly violated PA’s Right to Know law throughout the years-long process of trying to bully the plan through.
The recent Sylvan Avenue Trail meeting presentation did not even include a budget slide. How much money has the Sylvan Avenue Trail received as part of the MOC? How much is budgeted to address the major environmental and safety issues, like an abandoned mine under part of the project area?
Slides showed an unrealistic rendering of the trail with mature plantings to obscure removal of existing trees and gentle slopes instead of cliffs.
Some residents who arrived early said they were told city officials were holding a separate, closed-door meeting with PennDOT before the public meeting.
And according to Mr. Panzitta and Pittsburgh Neighborhood Services infrastructure engagement specialist Jan Raether, this was to be the only public meeting about the Sylvan Avenue Trail.
Unfortunately, this territory is all too familiar. It is obvious to us and others in Greenfield and Hazelwood that, although Mayor Ed Gainey canceled the MOC, DOMI has continued to plan out a buildout of the project.
What’s not missing from the Sylvan Avenue Trail project is red flags that point to a road paved with bad intentions.
Some residents of Greenfield and Hazelwood have organized meetings to discuss the project and reach consensus on an alternative proposal. Reach out to Junction Coalition at junctioncoalition@gmail.com if you are interested in getting involved.
On July 14, Pittsburgh’s Department of Mobility and Infrastructure (DOMI) hosted a virtual meeting about plans to tear down and rebuild Swinburne Bridge in lower Greenfield. The bridge, built in 1915 and rehabilitated twice, is in poor condition and had its weight limit lowered to 21 tons in 2014. According to the Swinburne Bridge project page on Engage PGH, it serves the communities of Four Mile Run (“The Run”), Greenfield, South Oakland, and downtown. The bridge connects Swinburne Street in South Oakland to Greenfield Avenue in lower Greenfield. DOMI said the city is working with the Federal Highway Administration and the Pennsylvania Department of Transportation (PennDOT) on the project.
About 65 attendees logged in to the meeting, plus an in-person “watch party” of 20 on the deck at Zano’s Pub House. Barb Warwick, who lives in The Run and is running for Pittsburgh City Council’s District 5 seat, facilitated questions from the group at Zano’s.
Representatives from DOMI, PennDOT, and private construction firm Alfred Benesch & Company all acknowledged that work on Swinburne Bridge will profoundly affect The Run. A significant portion of the neighborhood—and the only street providing vehicular access to it—lies directly beneath the bridge. DOMI painted a rosy picture of plans to minimize disruptions to the community while completing the project. But several aspects of the meeting fueled continuing mistrust among residents, who have years of experience with the city treating them as roadblocks to development projects that serve private interests.
A double standard for safety
DOMI project manager Zachary Workman responded with unequivocal commitment to unspecified comments in the chat about bridge safety concerns. “We are absolutely not going to have another bridge collapse,” he said, referring to the January 2022 collapse of Fern Hollow Bridge. “That can’t happen, and we’re not going to let it happen.”
Mr. Workman had more guarded answers to concerns raised by affected residents. He said DOMI is aware of dangerous traffic conditions along Greenfield Avenue that led to repeated requests for traffic-calming measures. “It’s definitely something that’s on DOMI’s radar for improvements in the future but they are going to be—it’s something that we’ll—it’s in the long-range plan as resources become available … It’s going to be a little while still and beyond the scope of this project.”
Project plans include a traffic signal at the intersection of Swinburne Bridge and Greenfield Avenue. When asked if a traffic signal could be installed sooner than the projected fall 2026 bridge completion, DOMI chief engineer Eric Setzler told residents, “Unfortunately, I think, it’s being constructed as part of this project. I certainly understand your desire to see it as soon as possible. I could definitely see that being beneficial, but it’s part of the project so it’s going to have to come at the same time as the rest of the project.”
“Property takes” not ruled out
Also in contrast with DOMI’s commitment to never let another bridge collapse, they went out of their way to avoid firm promises concerning homes and businesses beneath Swinburne Bridge.
Dana Provenzano, who owns two affected properties including Zano’s, asked, “You’re saying you’re not taking any properties, correct?”
“Our preliminary investigation into the demolition and construction is that this bridge can be demolished and rebuilt without taking homes,” Mr. Workman responded. “We’re in preliminary engineering, but that seems to be feasible.”
Asked whether Mayor Gainey’s promise changed plans for the bridge, Mr. Setzler said it “did help us clarify what we were doing for this project … Once we knew [the MOC shuttle] was no longer part of the equation we could home in on bikes, peds, and vehicles.” He did not specify what kind of vehicles.
Mr. Setzler explained that a couple of years ago, DOMI was considering new alignments that would eliminate the sharp turn on the northern end of the bridge. “However, as we were looking at it we realized pretty quickly that any different path for the bridge would require right-of-way, require property takes—by definition, because you’re going over a place where there wasn’t a bridge before.”
Pittsburgh’s 2023 capital budget includes $100K for right-of-way acquisition associated with Swinburne Bridge, but Mr. Setzler said that setting aside funds for this purpose is standard procedure on this type of project. “We believe we can avoid taking property, and that is our goal,” he added.
A shared-use path to nowhere?
Many MOC critics believe profiteers who dreamed up the plan are regrouping to use this bridge replacement as cover for an eventual revival of the community-erasing shuttle road.
Mel Packer of Point Breeze said he has ridden his bike across Swinburne bridge and appreciates “how dangerous it can be once you get onto the Oakland side.” Although he welcomed the “shared-use path” in DOMI’s presented design, Mr. Packer questioned why the path suddenly stops in that treacherous location.
“I’m old enough to remember we had a bridge to nowhere once,” he said. “I feel like this is the bike path to nowhere … What are you not telling me? Why would we build a path that wide across the bridge when it’s impossible to widen Swinburne [Street]? We know it’s impossible—I mean, it would cost many millions of dollars; you’d have to buy properties up on the hill, build a wall 50 feet tall. No one’s going to do that.”
Mr. Setzler responded, “The shuttle has been put aside; that is done. But we’re really looking at the bike-ped connection, and a couple of things we showed on the screen [slide 13 of the presentation]—just to be clear, they’re not part of this project.”
He described a desired off-street connection between the Eliza Furnace trailhead and Swinburne Bridge where the path ends. This could allow cyclists and pedestrians to travel “into the heart of Hazelwood” without navigating the five-way intersection at Greenfield Avenue/Second Avenue/Irvine Street/Saline Street.
An additional connection was not listed in the slide’s text. “There’s also a potential to maybe get on a trail on the other side of the road [where the path ends on Swinburne Bridge] and get back down into [Schenley] Park and go up through the park past the soccer fields and get into Oakland,” Mr. Setzler said.
This route corresponds exactly with the “Swinburne connection” referenced in DOMI’s October 2020 presentation as “phase 2” of the MOC. The projected 16-foot-wide road was to traverse the same landslide-prone hillside with fragile soil conditions that prevent Swinburne Street from being widened.
DOMI’s presentation on the Swinburne Bridge did not include a slide with ideas for future traffic-calming measures on Greenfield Avenue, even though residents must face speeding traffic every time they walk between their houses and cars.
Rushing past design, community input
Rob Pfaffman, a prominent local architect, called the Swinburne Bridge project “a hidden opportunity to celebrate the Hollow, the community, the natural environment, and the trail of course running through it.” But he said that based on what he saw in the presentation, planners are disregarding that opportunity.
“You can’t have a design process where you’re already through preliminary design and you haven’t engaged the community,” Mr. Pfaffman commented. “[Design is] integral to a great project, and right now what you’re showing us is not that. It’s a Fern Hollow Bridge—which is basically expediting a project as quickly as you can and saying screw the design.”
The next public meeting is not scheduled to be held until 2023 or 2024—during “final design.”
Pittsburgh’s Department of Mobility and Infrastructure (DOMI) held a public meeting on July 14 about the Swinburne Bridge project. Mayor Gainey’s neighborhood services manager, Rebekkah Ranallo, debuted as a co-facilitator.
Ms. Ranallo seemed genuinely excited to learn that about 20 residents of Four Mile Run (“The Run”) and their friends had gathered at their local pub to participate as a group in the Zoom-only meeting. “I think it’s great that folks are getting together for civic engagement opportunities like this,” she said.
During the Q&A session, attendees brought up a list of community demands (listed below) for a transparent public process. Ms. Ranallo assured them on behalf of DOMI and the mayor’s office, “We want to let you know that improving the way all of our departments do community engagement with our residents is a top priority.”
As the City of Pittsburgh begins “engaging” communities about this project, it’s important to understand why getting involved is a matter of survival for affected residents—and how they lost trust in local institutions tasked with serving the public interest.
In August 2015, Run residents learned of Mon-Oakland Connector (MOC) shuttle plans from a Pittsburgh Post-Gazette article touting an already-submitted grant application that turned out to be fraudulent. DOMI, created in 2017, initially claimed they were pushing the restart button on the MOC concept. But the restart got off to a bad start when DOMI organized a January 2018 public meeting to “share the potential alternative routes” for the MOC. Attendees reported that the exercise seemed designed to herd them toward a conclusion that only the Schenley Park route could work.
Over ensuing years, DOMI continued pushing the MOC on affected communities in a dishonest and non-transparent way. These are just a few examples:
On April 13, 2018, DOMI filed for a $1 million grant for work on the Sylvan Avenue trail, part of the MOC route, to make the trail suitable for MOC shuttles. At a public meeting the following month on May 22, DOMI did not mention the grant at all. When the grant was approved in July 2018 by the Southwestern Pennsylvania Commission, DOMI still did not inform affected residents. Asked about the grant and why DOMI kept it secret from residents, former DOMI director Karina Ricks said, “Well… we could have handled that better” and “It’s not possible for there to be some conspiracy—we’re just not competent enough for that.”
In August 2020, residents on Acorn Street near the Swinburne Bridge received a letter from DOMI and AWK Consulting Engineers citing eminent domain. When asked about this at the October 2020 MOC meeting, Ms. Ricks responded, “It is a letter written by a lawyer and, unfortunately, they do reference the right of eminent domain. The City has absolutely no intention to take properties [as part of the bridge construction]. There is a possibility there might be some slivers that will be needed to create new footings for the bridge.”
Residents obtained a 2018 request from DOMI to Pittsburgh’s Office of Management and Budget for funding. That document is mostly blank, but DOMI was nonetheless given $9 million of taxpayer funds. One section of the document DOMI did fill out was the section reading: Please identify the source of external funding and how the project adheres to the funding source’s rules and regulations. “Demonstrated support of the public” was a checklist item within that section. DOMI checked off this item and commented: Depends on which community!
Additional information received through resident-filed Right-to-Know requests, sources in city government, and expert independent consultations revealed the true “vision” behind the MOC and the nature of Hazelwood Green’s relationship to surrounding communities. Private interests have a long-term plan that calls for erasing The Run off the map so universities can expand from Oakland campuses to Hazelwood Green. And it includes using eminent domain to acquire resident homes and business.
A 2009 study from the Remaking Cities Institute of Carnegie Mellon University (CMU), Remaking Hazelwood, makes this intention clear:
“The urban design recommendations proposed in this document extend beyond the boundary of the ALMONO site. The end of Four Mile Run valley, the hillside and Second Avenue are all critical to the overall framework. Some of these areas are publicly-held; others are privately-owned. A map is in the section Development Constraints. The support of the City of Pittsburgh and the Urban Redevelopment Authority (URA) will be critical to the success of our vision. The ALMONO, LP could try to purchase these sites. Failing that, the URA can support the project by purchasing those properties that are within the scope of the recommendations and making them available for redevelopment in accordance with the proposed strategy.”
Unfortunately for existing communities seen by the authors of this report as “development constraints,” there is no evidence that underlying goals have changed for development in the area.
Public meetings about these projects have not shown improvement, either. DOMI originally scheduled the Swinburne Bridge meeting for June 16, but residents pushed back after finding out only 10 days in advance. The extent of DOMI’s outreach for that original meeting was a letter sent to a few residents, which those residents received on June 6. The rest of the community learned of the meeting through their neighbors who received the letter.
During a month-long lead-up to the rescheduled meeting, several residents asked DOMI to make the presentation (which they presumably would have prepared for the June meeting) available so the public would have time to review it in advance. None of the residents received a direct response from DOMI. About four hours before the start of the July 14 meeting, project manager Zachary Workman posted a statement in the Q&A section of the project’s Engage PGH webpage that DOMI would not honor the request.
Community demands shaped by experience
Residents have learned from years of MOC public meetings designed to check a “community engagement” box while minimizing the community’s effect on predetermined outcomes. The whole time, they were communicating ideas for better public engagement to DOMI—but DOMI ignored them. Residents have called for the following:
All meetings must be posted with a minimum of 14 days’ notice to allow working people to arrange their busy lives to attend and have their voices heard. The meeting information must be widely advertised on social media, sent to email lists, and communicated by any means necessary to community members who lack internet access.
The meeting presentation must be posted at the same time the meeting is announced. The public must be afforded sufficient time to review and understand the information being presented so they can come to the meeting prepared with questions. If you do not yet have the presentation ready, then you should postpone the meeting to give people a chance to review the presentation after you have posted it.
All meetings must include a Q&A session where every attendee is able to hear all questions asked and all answers given. The Q&A session itself should be expected to last at least an hour, if not two hours. All answers to questions should be thorough and truthful, with a clear plan for following up on information DOMI doesn’t have. The Q&A session must not be curtailed because of time constraints, especially if the presentation has taken up more than half the allotted time for the meeting. There is no reason the presentation should require so much time, especially since the public will have already had a chance to review it. Dialogue with the community should be the main focus of all meetings.
Meetings must offer an in-person option so that no community members are excluded.
Meetings with a virtual component must provide space for at least 300 virtual attendees so that no one is unable to access the meeting at any time.
After the meeting, a recording of the Zoom meeting and the chat transcript must be made available on the Engage PGH website.
Ms. Ranallo said at the July 14 meeting, “While I can’t speak to each item on your list of demands, we do want to build trust with you … We have a new administration, we have new leadership at DOMI, and we ask that you give us a chance to try to earn that trust.”
The community’s demands were compiled as a road map the city can follow to do exactly that.
On April 26, Pittsburgh’s Department of Mobility and Infrastructure (DOMI) hosted a meeting via Microsoft Teams to kick off public engagement on its Sylvan Avenue Multimodal project, presenting early plans and fielding questions from community members.
Many of those questions revealed concerns about the project’s limited scope, its priority level and timing, and its potential effects on residents along Sylvan Avenue.
A project within a project
The Sylvan Avenue Multimodal project is one part of a pedestrian/cyclist trail that replaces—but follows the route of—the controversial Mon-Oakland Connector (MOC) shuttle road between Greenfield and Hazelwood avenues. The stretch of Sylvan Avenue between Home Rule Street and Greenfield Avenue (currently closed to traffic) is also part of the trail but considered a separate project.
According to DOMI project manager Michael Panzitta, the City of Pittsburgh received a $1.76 million state grant to restore the closed part of Sylvan Avenue for bikes and pedestrians only. Along with separate funding, work on the Home Rule-to-Greenfield stretch of Sylvan Avenue will come with its own set of public meetings.
Discussion at the April 26 meeting was limited to plans for Sylvan Avenue between Home Rule Street and Hazelwood Avenue.
That work includes reconstructing the sidewalks, repaving the street, and adding features to slow down traffic. Two of the biggest traffic-calming features are raised pedestrian crosswalks at two sets of city steps, and landscaping near the entrance to the trail.
In addition, Sylvan Avenue is set to be designated as a Neighborway street, meaning it is a low-traffic street designed for the needs of people on foot, bikes, or other nonmotorized vehicles.
A combination of city and federal funding
The City of Pittsburgh is funding the design phase and street repaving. Construction funding comes from a federal grant with Pennsylvania Department of Transportation oversight, explained Leon Jeziorski of Michael Baker International, the multimodal design firm for the project.
Mr. Panzitta was unclear on the source of federal funding. In a May 9 email, he referred funding questions to Emily Bourne, DOMI communications specialist. Ms. Bourne replied to emailed inquiries that she was coordinating her response with that of Mayor Gainey’s press secretary, Maria Montaño, who had been contacted separately.
Community concerns include parking, safety
During the Q&A portion of the meeting, residents raised concerns about pedestrian safety on Hazelwood Avenue and the limited parking available on Sylvan Avenue.
Pastor Tim Smith, CEO of Center of Life—located at the intersection of Hazelwood and Sylvan avenues—asked if the project will widen the road. He said people park on both sides at that end of the street, which leaves a narrow space for drivers passing in opposite directions. Mr. Jeziorski responded that the project would not address parking issues, and the east side of the street (across from the Center of Life) is currently a “no parking” zone.
A Sylvan Avenue resident who did not give her name said enforcing the “no parking” zone would prevent residents from parking near their homes.
Roy Simms, who said he’d lived on Sylvan Avenue for more than 50 years, asked if the city steps would be repaired as part of the project. Mr. Panzitta answered that the steps are also outside the project’s scope.
Why here, why now?
Several attendees wanted to know more about why this project was identified as a priority now. Despite being touted as a safe multimodal connection, it does not address issues with the steps, the decrepit retaining wall and railing near the future trail entrance (the project will use landscaping to block off the railing rather than fix it, according to Mr. Jeziorski), or dangerous conditions at either end of Sylvan Avenue.
“If you’re looking to increase bike accessibility in a safe way, there’s a lot of already-existing safety issues with Greenfield Avenue,” said Eric Russell, a Greenfield resident and daily bike commuter. “Especially if you’re dumping people onto Greenfield Avenue from Hazelwood.”
Catherine Adams lives on Hazelwood Avenue and said some of her neighbors have been hit by cars. They have been meeting with DOMI and District 5 Councilman Corey O’Connor about speeding and safety issues on Hazelwood Avenue for the past two years.
Mr. Panzitta said the trail is included in the Greater Hazelwood Neighborhood Plan. Page 96 lists “creat[ing] a bicycle route up the hill from and parallel to Second Avenue” as a way to “address gaps in multi-modal network throughout the neighborhood.”
Mr. Jeziorski defended the project, asserting that improved accessibility to this corridor will draw more residents and businesses to the neighborhood. The increased activity should help Hazelwood get grant funding to replace the steps. “So this is a building block that can help with other improvements in the future,” he said.
Recent Comments